KIIDP II Road Works at 25% Completion- KCCA John Babiiha Road 3 1 Top story

Eng. Stephen Kibuuka, the KCCA project coordinator, says the percentage covers majorly low value works like transfer of utilities and clearing drains.
11:19
11:19

City Road Works to Resume with Minimal Workers Stephen Kibuuka 1

According to the Project Coordinator from KCCA Eng. Stephen Kibuuka, the lock-down was abrupt leaving both KCCA and the contractors without a plan to continue operations immediately.