From delivering a Final Investment Decision, the commencement of field development, and the arrival of the rigs, there is hope that Tilenga and Kingfisher Developments in the Albertine will deliver first oil in 2025.
Following
the Final Investment Decision, the commencement of field development, and the
arrival of the rigs, there is hope that Tilenga and Kingfisher Developments in
the Albertine will deliver the first oil in 2025.
The joint venture partners, TotalEnergies, China National Offshore Oil
Corporation (CNOOC), and Uganda National Oil Company (UNOC), announced a
final
investment decision (FID) at the beginning of February marking a
major step in the country’s oil sector.
The FID covered the Kingfisher and the Tilenga development projects (Upstream)
and the crude oil export pipeline or East African Crude Oil Pipeline (EACOP).
Some of the players in the sector had expressed their frustration with
the slow pace of developments from 2006 when commercial quantities of oil were discovered
in the Albertine.
The sector has been characterized by long negotiations, tax disputes with
companies like Tullow, and the COVID-19 pandemic. There has been a shift in
dates set for the first oil from 2009, to now 2025.
The Director
of Petroleum at the Energy Ministry, Honey Malinga told URN that the FID had
what he described as a “trigger effect” leading to a beehive of activities in
the Tilenga and Kingfisher areas.
“The final investment decision was a key achievement for the three projects.
From EACOP, Tilenga, and the Kingfisher. So we started on a good note
though in September we had issues with the EU resolution. But generally, the
year has been good for the industry,” said Malinga.
Earlier the year, PAU’S, Executive Director. Earnest Rubondo told journalists
that 2022 was going to commence the period of three years of intense
infrastructure development in preparation for the first oil in 2025.
Rubondo had predicted that investments in the sector were likely to shoot to $3
billion compared to S$ 230 million in 2019, $ 180 million in 2020, and $ 500
million in 2021.
Investments are expected to increase to about US $ 3 billion in 2022. The
Authority had indicated that contracts that were to be awarded in 2022 were
estimated at $6 billion. The Petroleum Authority has estimated that
between $15-20 billion to be invested during the development phase of the oil
sector.
“Ugandans need to get excited and prepare for what is coming ahead, and the
transformation it is already bringing,” said Rubondo.
Rubondo
suggested that 40% of the $15-20 billion to be invested during the development
phase will be retained through national content. A number of Ugandan
suppliers were already partaking part of that pie, said Emmanuel Mugarura, the
CEO, the Association of Uganda Oil and GasService Providers (AUGOS)
“Yes, people are getting money. Unfortunately, most of the money is not being
kept here. Most of the money is going to other countries. Why? I don’t know
outside countries. But mainly because other people seem to be more prepared
than we are,” said Mugarura.
Researchers from the Economic Policy Research Centre (EPRC) working on a study
to identify linkages between the agriculture sector and the oil and gas sector
in July found that the influx of people to the Albertine region had led to a
shortages supply of meat, vegetables, and milk in the Albertine.
“If you consider the core oil districts and spillover districts, you find that
the rate at which demand is growing is faster in the core districts than the
spillover districts,” explained Moses Odonkonyero, the research lead.
Developments at CNOOC’s Kingfisher and TotalEnergies’ Tilenga The conclusion of
the key agreements towards the end of 2021, the enactment of laws on taxes and
taxation, and the FID propelled the industry to procurement and contracting.
Contracts for the preparation of the Kingfisher and Tilenga industrial
areas were awarded to Excel Construction and Mota-Engil
Uganda respectively.
As the year ends, sources told URN about 90% of the work had been completed by
Mota-Engil
Uganda. Facilities to be hosted in the industrial area for Tilenga include the
Central Processing Facility(CPF), construction camps, and drilling and
operational support bases among others.
At the end of 2021, preparation of the site at the Tilenga area was
estimated at about 30% but a source at TotalEnergies told URN the contracted
companies were in the advanced stages of the work.
Mota-Engil
Uganda had by early this commenced preparation of the site for the Central
Processing Facility.
Mota-Engil Uganda also won the contract for the construction of 31 well
pads on which the wells for the Tilenga project will be drilled. . According to
the plans, drilling at the Tilenga Project should have commenced during the
last quarter of 2022.
Drilling
companies for the North-Nile pad in the jobi-rii area were already on the
ground. Actual drilling is expected at the beginning of February 2022.
Kingfisher Development under CNOOC URN has been visiting the Kingfisher
project where China’s Offshore Oil Engineering Company (COOEC), and partners
are developing the Mputa,
Nzizi and Waraga fields. Kingfisher will host
a Central Processing Facility (CPF) with a capacity of 40,000 barrels of oil
per day.
There will also be Thirty-one wells to be drilled on four well pads.
With FID, the Buhuka area along Lake Albert shores has greatly changed with a
number of visible from February to date.
The well pads, and in-field access roads are being constructed by Excel Limited
Three well pads are to be constructed in the Kingfisher development by Excel
Construction limited. The contract to design and construct a permanent camp,
supply base, and safety and security check was awarded to China State
Construction Engineering Corporation.
CNOOC Uganda, the operator of the Kingfisher project had by early December
erected a rig on location, on the western part of Lake Albert. Energy and
Mineral Development Minister, Ruth Nankabirwa visited the project in
mid-November to assess the progress.
President
Museveni was scheduled to flag off drilling at the Kingfisher on December 20th,
2022 but the event was called off. Sources indicate that the change of date was
due to pending work on the waste management facility for drill cutting.
The drilling waste Treatment and Disposal facility at Kingfisher is to be run
by Luwero Industries a subsidiary of National Enterprise Corporation (NEC), the
commercial of the ministry of defense/ UPDF.
The UPDF is partnering with a Chinese firm HBP. Source told URN that while
Luwero Industries has already been established on the ground with a camp to
house 150 people, the facility which should have equally been commissioned by
the President still had some issues related to the power supply.
Former Deputy IGP, now General Manager of Luwero Industries, Major General
Muzeeyi Sabiiti was at Kingfisher on November 30th to check on the progress and
to ensure compliance with environmental requirements before drilling starts.
2022 was one
of the most tumultuous years for the East Africa Crude Oil Pipeline (EACOP).
While Uganda and Tanzania were determined to move with the project, 2022 saw an
intensification of campaigns against it by anti-fossil campaigners targeting
insurance firms, and banks among others. The campaigners in September secure an EU
Parliament’s urging for the Delay of EACOP.
The efforts
had tried to stop financing for the development of EACOP, whose estimated cost
is between $3.5 billion to $5 billion. PAU, Director Support Services, Penina
Aheebwa in September defended EACOP saying those fighting its development were
against the development of Uganda.
“They should be aware of the value of over US$ 81 billion (almost double
Uganda’s current GDP) at stake from Uganda’s oil and gas projects.
Additionally, the perceived environmental impacts have been fully addressed
through the established Environment and Social assessment (ESIA) processes to
the highest international standards,” said Aheebwa in a statement.
Ruth Nankabirwa, and her State Minister, Okasai Opiolot have been at global
fora including COP27 to defend EACOP and the developments in the Albertine.
Despite the negative campaigns. there were signals that the project’s construction
could take off in 2023.
During the year, the EACOP got some funding totaling $300 million from
alternative lenders like the Islamic Development Bank and $200 million from the
Afriexim Bank. In October, Afrexim Bank chairman, Prof Benedict Oramah, and his
executive team said financing EACOP and the refinery in Uganda was a strategic
business that will uplift African economies' armory to fight poverty.
In July, the East African Pipeline Crude Oil Company(EACOP) Ltd General
Manager, Martin Tiffen applied for a construction permit from Uganda and
Tanzania. The Ministry of Energy was yet to grant the permit by the time of
filing this report.
Petroleum Director, Honey Malinga told URN that while no objection had been
received from the public, the ministry was in final stages of the exercise to
ensure compliance with Environmental, Social, and Governance.
“The law says 106 days. So we expect a decision late this month or early next
year. Because I think there are some conditions that they never fulfilled at
the beginning. They were supposed to make the application with payment but they
didn’t,” said Malinga
//Cue in “They were supposed to....
Cue Out..... to the cabinet then conclude the process”//
Section 12 of the Petroleum (refining, conversion Transmission, and storage)
Act requires the government to carry out public hearings on such projects
before a decision is taken on whether allow the construction.
The notice in the case of Uganda was in relation to about 296 kilometers of the
pipeline on the Uganda side starting from Kabale in Hoima up to Mutukula border
with Tanzania.
Exploration Uganda’s petroleum resources remain at 6.5 billion barrels in place
with about 1.4 billion barrels as recoverable. No more discoveries were
reported.
“These resources, much as they look very small compared to the large producers
are a very good beginning for the country. Because they will enable the
production of 200,000 barrels of crude oil per day for the country. And it is
important to note that these resources are in only 15%of Albertine Graben which
is currently licensed” said Rubondo.
According to Rubondo, there is potential for more oil to be discovered in 2023
from the ongoing exploration being undertaken by Oranto Petroleum and
Australia’s Armour Energy in the Ngasa and Kanywataba contracts.
Meanwhile, the Ministry of Energy was yet to complete the licensing of
additional areas for exploration. The second licensing round that was partly
affected by the COVID-19 pandemic has dragged on since 2019 when the ministry
invited bidders.
URN has learned that while the Ministry had zeroed in on two successful
companies which included Uganda National Oil Company(UNOC), the cabinet was yet
to endorse the deal.
“The Minister has to let the cabinet know about the process before we
sign. So we have two companies waiting for us to get a green light from the
cabinet before we can award the licenses” revealed Malinga The two companies
include Uganda National Oil Company UNOC and DGR Global.
One of the lows of the sector has been the delay of an FID for the Kabaale
Refinery project which had been expected by early February 2022. The 60,000
barrels per day (BPD) oil refinery was supposed to be connected to Kampala by
pipeline to cater to the local supply market of diesel and gasoline.
At the end
of the US-Africa Leader’s summit, there were reports by the State House that
Albertine Graben Refinery Consortium (AGRC) has reached an agreement on capital
investments.
Government in April 2018, signed a Project Framework Agreement (PFA) with the
Albertine Graben Energy Consortium (AGEC), for the design, financing,
construction, and operation of a 60,000 refinery in Hoima, Uganda. The
AGEC contracted SAIPEM S.p.A to undertake a Front-End Engineering Design (FEED)
for the project.