Warning: Trying to access array offset on value of type bool in /usr/www/users/urnnet/a/story.php on line 43 Construction of UGX 23b Kitgum Main Market Resumes :: Uganda Radionetwork
The construction of Kitgum Main Market has resumed. This comes three weeks after construction of
the multi-billion market was temporarily halted over surge in cases of
Coronavirus (Covid-19) in the country and lockdown restrictions instituted by
the government.
Alfred Alexis Abonga, Kitgum Municipal Council Engineer told Uganda Radio says that
some of the technical officials were left stuck in Kampala while some materials
were not readily available at the time lockdown was instituted.
He says the contractor, China State Construction Engineering Corporation
Ltd also found it necessary to temporarily halt works after cases of covid-19
increased in the district and around the country.
“When Lockdown was instituted, it found some of the technical staffs like the
Project Manager in Kampala, it meant he had limited supervision, also covid-19
cases worried them a lot and made them halt works,” he said.
Abonga however notes that following the three weeks of no works, the contractor
finally resumed work after acquiring the necessary materials like cement and
reinforcement bars.
//cue in: “I want to…
Cue out:…at the moment.”//
Abonga says despite the temporary halting of construction for the past three
weeks, the progress of works is promising and currently at 70 percent adding
that he anticipates the contractor will beat the November 30 contract deadline.
//cue in: “I’m happy the…
Cue out:… all going on.”//
Kitgum Main Market was meant to be completed by July this year after its
construction commenced in June 2019.
The Local Government Ministry however extended the contract for the
construction of the 23 billion shillings’ market in April by five more months
till November 30 following requests made by the contractor through SABA
Engineering PLC, the project consultant.
The contractor in a report to the government highlighted challenges ranging
from the Covid-19 pandemic in March 2020 that saw suspension of work on-site
and heavy rainfall, which affected work on Block B.
They also highlighted the adverse ground conditions, where the
contractor encountered groundwater in the foundation, which was not in the site
investigation reports and the resultant designs.
Currently, the contractor has so far made progress on Block A where they are
finalizing with roofing, beam filling, walling, construction of stalls, and
electrical installation.
The Market is expected to accommodate more than 200 vendors who will occupy
1,500 stalls and over 600 lockup shops once its construction funded by the
African Development Bank-AfDB is completed.