The justices unanimously ruled that the nine people Paul Peter Etot, Deo Okekllo, Kiden Santa, John Paul Omara, Francis Chira, Isaac Otim, Steven Etot, Albert Elwa and Ruth Etot should instead be compensated with 203 .2 million shillings as general damages.
Karuma Hydro Power Site
The
Court of Appeal has quashed the decision by the High Court to award 9.3 Billion
Shillings as compensation to claimants of land where the government is
currently constructing the Karuma Hydro Power Project.
A panel of three justices Christopher Izama Madrama, Irene Mulyagonja and
Monica Mugenyi has set aside the award issued to nine people by the High Court
Judge Andrew Bashaija.
The justices unanimously ruled that the nine people Paul Peter Etot, Deo
Okekllo, Kiden Santa, John Paul Omara, Francis Chira, Isaac Otim, Steven Etot,
Albert Elwa and Ruth Etot should instead be compensated with 203 .2 million
shillings as general damages.
In 2015 the nine people sued the Attorney General and Sino Hydro
Corporation Limited for compulsory acquisition of their two pieces of land
measuring approximately 8.109 hectares and six hectares at Nora Kamdini in Oyam
district.
The land was acquired between 2011 and 2012 for the construction of the
Karuma falls Dam by Sino Hydro Corporation Limited for the land measuring 8.109
hectares out of which a portion measuring 3.705 hectares was compulsorily
acquired for the construction project. The remaining part of the land which
falls outside the construction project was used as a dumping site and an access
route by the construction firm.
However, the two pieces of land have rocks whose quantity and valuation was disputed
by the nine. The petitioners were then awarded
1.2 billion Shillings as the market value of the suit land, 8.3 billion
shillings as the value of the rocks on the land and 1 billion Shillings as the
costs of the case.
The Attorney General appealed arguing that the award of 1.2 billion as
compensation for the land and all properties on it was exorbitant because the
claimants had stated the value of the land as 701.5 million Shillings based on
their professional valuation report.
The government also faulted the judge for having erred in law and fact in
holding that the compensation is payable for rock deposits on land and that
rocks are compensated separately from the value of such land and that at the
same time he held that rocks are part of the land.
The Judge was also faulted for having gone ahead to award the 8.3 billion
shillings as the price of the rock deposits which the government argued that
the figure was reached upon based on speculation that the claimants were
engaged in the business of rock exploitation and extraction of quarrying.
The government argued that the High Court did not consider the circumstances of
the case in awarding general damages. The Attorney General said that the Judge
ought to have considered that the suit property was acquired in the public
interest for the legitimate purpose of constructing the Karuma Dam for the
benefit of all Ugandans the petitioners inclusive.
Court also heard that under the Land Act, unlike buildings and crops, which are
valued and compensated separately, from the value of the unimproved land, rocks
sand and clay constitute part of the Land and ought not to be valued and
compensated separately.
Accordingly, Attorney General Kiryowa Kiwanuka who argued the case with Assistant
Commissioner Patricia Mutesi and State Attorney Jackie Amusogot asked the court
to quash Justice Bashaija's judgement.
In their lead Judgement written by Justice Madrama, they have set aside the
award on grounds that there was no basis to give an award higher than the value
of the acquired land.
According to the Justices, the assessment of the land was done and specifically,
the value of the land was put at 250 million shillings together with the cost
of processing title at 6.3 million Shillings and crops and houses that were
there were also valued and the government paid 813 million shillings which was
much more than their value of the land.
However, they added that when the government wants to compulsory acquire
land, it should compensate the owner before the possession or acquisition but
this was not the case and therefore he had to award the claimants general
damages for breaching Article 26 of the Constitution.