Now, in its findings the Committee notes that although the structure of the main bridge is sound and lacks any defects, the surface of the bridge was affected by the failure of the asphalt concrete and the liquid to bond with the water proofing solution known as Sikalastic.
Color illumination at the source of the Nile bridge in Jinja district.
Deprecated: trim(): Passing null to parameter #1 ($string) of type string is deprecated in
/usr/www/users/urnnet/a/story.php on line
663
Contractors of
the newly built Jinja Bridge used a new form of technology of road surface
construction that is still under trial, a report by the Physical Infrastructure
Committee of Parliament has revealed.
The new bridge
that was built by Joint Venture of Zenitaka Corporation and Hyundai Engineering
and Construction Co. Ltd across River Nile in Jinja district cost USD 112
million.
However, the
surface of the bridge developed defects 10 days after it was commissioned on
October 17th, 2018 drawing public outrage.
As a result, parliament tasked the Physical Infrastructure Committee to investigate and establish what could have happened.
Now, in its
findings the Physical Infrastructure Committee notes that although the structure of the main bridge is sound and lacks any defects, the surface of the bridge was affected
by the failure of the asphalt concrete and the liquid to bond with the water proofing solution known as Sikalastic.
The report authored by the Committee Chair, Robert Kafeero
Ssekitoleko, notes that in order to ensure the longevity of bridge deck, a
4-millimeter synthetic waterproof membrane was used in between the concrete bridge
deck and 70-millimeter-thick asphalt wearing course.
However, due to lack of
proper bonding, the asphalt surface was unable to withstand the shearing force
applied to it by the passage of traffic. The committee then learnt that this technology was new and
still being tested there by questioning the decision to apply it on a modern
bridge.
Ssekitoleko says works were still ongoing on the trial section using the
modified track coat and the trials are expected to go on for between eight to
ten months.
He says if the
technology doesn’t work, Government and the contractor may be forced to go back
to the old technology where no bonding material or water proofing material will
be used.
“The implication of reverting to the old system would be that the life
span of the newly constructed bridge would reduce from 120 years as envisaged
to between 60 and 80 years,” the committee report reads.
The report
notes that if the tests yield successful results, the entire surface of the new
bridge will be overhauled and worked on at the cost of the contractor.
However,
the committee notes that the technology has failed in some places like on the
Nagoya express in Japan, the long Bridge in Hanoi Vietnam and Thaun Phuoc
Bridge over Han River in Vietnam among others.
The committee
deems the technology unsustainable given that it hasn’t been successfully applied
anywhere without experiencing defects in a very short term.
The Committee
also observed that the consultant and contractor fell short of the task
expected of them since they failed to meet the technical specifications to have
the best quality materials suitable for the bridge.
The Committee has recommended to Government to review the
project to establish the capacity and lifespan of the bridge.
“The
Committee feels that there wasn’t enough detailed preliminary investigations
done before the inception of the Source of the Nile Bridge project. The
Committee is constrained to believe that there was laxity on the side of Uganda
National Roads Authority (UNRA) to closely supervise and monitor the work of
the contractor on the new Bridge,” reads the report.
The committee notes that even after rehabilitation, which
cost the contractor up to US$ 1.3M, the surface of the bridge is so rugged and
thus makes it unpleasant to drive due to protuberance on the surface level of
the bridge.
Dr. Masooki
Tatsumi, the Project Director in Charge of Supervision of the Project, informed
the Committee that there is no perfect solution for the bonding of the sikalistic
materials, adding that that there is need to test the material and make
improvements due to different weather conditions and traffic flow in different
countries.
Freelancer
Deprecated: trim(): Passing null to parameter #1 ($string) of type string is deprecated in
/usr/www/users/urnnet/a/story.php on line
766