The Lamwo district LCV Chairperson Sisto Oyet Ocen says the contractor was handed the site in July 2021 but immediately abandoned the project works and numerous efforts to reach out to their management on the work inception and progress have been to no avail.
Authorities of Lamwo district have
expressed concerns after a contractor who abandoned the construction of Pagada
Bridge in Palabek Kal Sub County right at the start resurfaced at the end of the contract period ostensibly to embark on the works
after abandoning the site a year ago.
The contractor, Hardscreen Logistics
Ltd was procured last year by the district
through funding from the Development Response Displacement Impact Project
(DRDIP) at a cost of shillings 2.5 billion to build the Pagada Bridge that
collapsed in 2018 due to heavy traffic.
The Lamwo district LCV Chairperson Sisto Oyet Ocen says
the contractor was handed the site in July 2021 but immediately abandoned
the project works and numerous efforts to reach out to their management on the
work inception and progress have been to no
avail.
Ocen however says they were only surprised to learn that this week the contractor had stealthily returned into the district and
started the process of bush clearing at a time when their contract timeline is
left with only one month to elapse.
According to Ocen, the District Executive Committee had
already recommended the termination of the contract in a bid to source for
another competent contractor to take over the project works.
//Cue in: “contractor mo ma….//
Cue out: …..handling loke,”//
The
Chairperson of the Project Committee, Francis Okello Jogo accused the contractor of incompetence having failed to
meet the entire obligation under the contractual terms and conditions
particularly on flouting the project completion timeline.
According to Jogo, they had signed a one-year contract on
the 21st July 2021 with Hardscreen Logistics Ltd with anticipation
that the project works would be completed and subsequently handed over to the
community by August 2022.
//Cue in: “wan wamiyo tic….//
Cue out: …..dwe me aboro.”//
Jogo says the act of abandoning the project had angered
leaders and residents in the area who have since 2018 when the bridge collapsed been facing enormous challenges of accessibility and mobility.
“Locals had heaved a sigh of relief and hoped that the bridge
construction would solve many challenges they have since been facing including
walking long distances to access health facilities, markets and other social
services,” says Jogo.
The
Lamwo District Chief Administrative Officer Felix Alex Majeme acknowledges the
concern, saying abandoning the site and delays in completing the projects without any genuine explanation is an
indication that the contractor was not committed to accomplishing the task.
Majjeme says the district has
already sought advice from the office of the Solicitor General on an impending
proposal of terminating the contract and re-advertising the bridge construction
works.
When contacted for comment, the
project manager at Hardscreen Logistics Ltd, Isaac Alemi declined to comment on
the matter saying he would get back to URN at an appropriate time.